Background

A high-population state struggled to implement major IT projects across various state agencies. The projects routinely experienced delays, cost overruns, or even full stoppages. The state’s IT agency sought an independent analysis of the root causes of these failures and recommendations to avoid them.

Pain Points

Outside technology vendors did not fulfill their obligations.
The state IT agency could not “right the ship” when projects went awry.
Contracts did not provide the state with the leverage to hold vendors accountable.
Lack of veteran project managers and subject matter experts to lead tech procurements.
Lack of adequate communications/coordination between state agencies and the IT agency.

Solution

Sol interviewed numerous stakeholders in the state government to analyze the processes for IT procurement, planning, governance, and delivery. Our team also reviewed contracts, procurement artifacts, project documentation, and governance materials for five troubled IT projects across the state. Root cause analysis and issue identification were used to find common problems.

Services

Sol Sprint 0 discovery program
Stakeholder interviews
Root cause analysis
Documents and contracts analysis

Talent

Engagement partner
Government subject-matter expert
Government contracts expert
Business analyst

Sol identified cross-agency communications issues, governance gaps, and a lack of experienced project management to guide overly complex programs that relied on large procurements and 3-5-year delivery timelines. Sol proposed several recommendations broken down into “quick wins,” or medium-term and long-term restructuring, including new protocols for contracting future IT projects. Sol recommended creating new positions within the state’s IT organization for seasoned project managers to oversee implementations across state agencies and ensure best practices are established.

The Results

SDLC Standard: Sol proposed a software lifecycle development standard that the state could use across future technology implementations.
Model Contract Design: Sol designed a modular template contract for future IT procurements, including more rigorous oversight and vendor process mandates.
New Project Delivery Management Model: Sol recommended a new structure for a project delivery office, with stronger risk management protocols and automation to replace complex paperwork.
Program Sequencing: Sol designed a plan to break large, multi-year projects into multiple proof-of-concept steps to help course-correct troubled programs.